Skip to content Skip to footer

Brinny Cork Grange Solar

PUNCH provided Planning Stage Civil and Traffic Engineering services for this new solar development at Innishannon, Brinny, Co. Cork. The proposed solar PV plant is intended to provide a direct wire renewable electricity supply to the MSD Brinny Pharmaceutical Plant located to the south of the site. The proposed PV plant is designed to provide a peak output of 8MW and will comprise up to 15,000 modules.

PUNCH prepared a site-specific Flood Risk Assessment, Construction Environmental Management Plan, and a Construction Traffic Management Plan for the development on behalf of the client.

Client:MSD IrelandArchitect:N/AValue:ConfidentialServices Provided:Civil Engineering, Traffic & Transport EngineeringCategory:Renewable EnergyProject Duration:2023Share